What is the net result of reducing the duration of a task (crashing) not on the critical path

11) What is the net result of reducing the duration of a task (crashing) not on the critical path?
A. Decreased project overhead costs
B. Reduced likelihood of liquidated damages for late delivery
C. Increased slack time associated with the task
D. Reduction in the project duration